Bulk activity and milestone move
There may be times when there is a project delay that affects all upcoming activities. In these cases, you can delay all the activities and milestones using the contextual menu:
- Right-click a cell or press and hold on a touchscreen.
 - In the menu, select Delay tags.
 - A dialog will appear with:
- Move day tag selector — choose how many days to delay the tags (1–20).
 - All lanes toggle — enable this to delay not only the tags in the selected lane, but all lanes starting from that day forward. This may take some time and a progress indicator will appear.
 
 - Click Save to move the activities and milestones or Cancel to discard changes.
 
Notes:
- Nialli™ Visual Planner automatically respects workdays, so moved tags will land only on valid days — even when shifting part of an activity. Tags can be manually moved into nonworking days.
 - Dependencies, including inter-lane ones, are preserved.
 - When shifting tags forward, enter the number of days.
 - Both undo and redo actions are supported.