Move activities and milestones in bulk
Project delays can affect multiple activities across your plan. To keep your schedule aligned, you can delay all activities and milestones at once. You can also shift all activities backward using the contextual menu.
- Right-click a cell or press and hold on a touchscreen.
- In the menu, select Shift tags.
- A dialog will appear with:
- Move day tag selector — Choose the number of days to shift the tags (1-20). To move tags backward, click the < icon to create a negative value. The selected value determines how many days the activities will be shifted.
- Apply to all lanes toggle — enable this to delay not only the tags in the selected lane, but all lanes starting from that day forward. This may take some time and a progress indicator will appear.
- Click Save to move the activities and milestones or Cancel to discard changes.
Notes:
- Nialli™ Visual Planner automatically respects workdays, so moved tags will land only on valid days — even when shifting part of an activity. Tags can be manually moved into nonworking days.
- Dependencies, including inter-lane ones, are preserved.
- When shifting tags forward, enter the number of days.
- When shifting tags backward, enter a negative value representing the number of working days to move the activities.
- Both undo and redo actions are supported.